Camp Catitipan, Davao City
UPDATES ON REMD
|
| PROJECT | COST | DATE STARTED |
% ACCOMPLISHMENT
|
REMARKS |
| Expansion of PRO11 Grandstand |
2.5 M |
May 21, 2010 |
9% |
ON-GOING |
| Construction of Monkayo MPS |
3,958,000 M |
Oct. 13, 2009 | 88% | ON-GOING |
| Construction of Montevista MPS | 4,458,000 M | Nov. 05, 2009 | 80% | ON-GOING |
| Construction of Manay MPS (PH 2) | 2,764,500 M | Feb. 01, 2010 | 100% | COMPLETED (JUNE 08, 2010) |
| Construction of Boston MPS | 4.2 M | Aug. 10, 2009 | 85% | PENDING |

MONKAYO MPS, MONKAYO COMVAL PROVINCE MONTEVISTA MPS, MONTEVISTA COMVAL PROVINCE


MANAY MPS, DAVAO ORIENTAL (PH 2) BOSTON MPS, DAVAO ORIENTAL
NON-PNP FUNDED FUNDED PROJECTS